Ray St. reopens to traffic a week early

Print
Email
|

by KREM.com

KREM.com

Posted on July 25, 2014 at 11:34 AM

Updated Friday, Jul 25 at 5:20 PM

SPOKANE, Wash.-- Road crews wrapped-up work nearly a week ahead of schedule Friday morning and reopened Ray Street to traffic on the South Hill in Spokane.

Crews closed both lanes of Ray street between 20th and 21st Avenue and diverted traffic to Freya Street while they connected a new 1-million-gallon tank to the existing sewer line.

READ: Ray St. closure to last nearly 3 weeks

The City of Spokane said the goal of the project was to reduce overflow from the combined sanitary and stormwater waste system. Crews initially expected the project would take about 14 business days to complete.

 